Product Description

saveBOARD Multi-Use is a semi vapour permeable structural composite panel made from 100% shredded and compressed post-consumer composite packaging and soft plastics. No water, glues, resins are used during the manufacture process. saveBOARD Multi-Use is finished with a clear (white or black) recycled plastic face and recycled paper back.

​

Not Perfect

saveBOARD products are made from 100% recycled waste and as such are not perfect. The dimensional tolerance is + / - 1mm and the weight + / - 10%/sheet.

 

The surface of MultiUse may have veins or press marks, the paper backing may be have creases and some air bubbles may be evident.

 

The colour will vary slightly from batch to batch due to the varying nature of the raw materials to manufacture saveBOARD, namely recycled waste. The colour may also vary slightly from a sample.

​

These are standard characteristics of a saveBOARD product. More information can be found here on the website (Not Perfect).

​

Scope of Use:

  • As an internal wall lining or partition in ventilated industrial spaces (ie sheds/warehouses).

  • As a wall bracing element - installation must be in accordance with Scion P21 test assembly, detailed in this guide under “Installation Bracing Wall”.

  • On timber or steel framing.

  • In wind zones up to and including Extra High as defined in NZS 3604:2011.

  • In earthquake zones as defined in NZS 3604:2011.

  • Where Materials Group 3 is required.

​

Limitations:

  • Not suitable for wet areas as defined by the NZBC E3.

  • Not recommended in confined spaces (made from post-consumer waste which creates a slight odour).

  • Do not use in permanent exterior applications (can be used as a temporary hoarding).

  • Check compatibility with any glues, resins sealants or building wraps to be used in conjunction with Multi-Use

  • Framing to be at a moisture content < 16% before internal linings are applied. This is a saveBOARD warranty requirement.

​

Handling

When manually handling saveBOARD Multi-Use ensure the panels are lifted correctly. For safety, we recommend a minimum of 2 people.

​

Storage

When stored internally on-site lay flat on suitable bearers. The spacing between the bearers should be no more than 600mm apart.

 

When stored externally on-site, there must be a minimum of 50mm clearance from the ground and water sources. If delivered sheets are stored outside prior to use they MUST be covered with temporary waterproofing.

 

It is good to trade practice to allow sheet materials to climatize to the site conditions for 48 hours prior to Installation.

​

Maintenance & Warranty

Multi-Use panels are inherently mark resistant, durable and suitable for high impact areas with a wipe down surface. Please refer to the Maintenance & Warranty (15yrs) documents on the saveBOARD website.

Installation Instructions

Working safely with saveBOARD

All saveBOARD products are safe to work and live with. All saveBOARD products are Volatile Organic Compounds (V.O.C.'s) and formaldehyde free.

​

saveBOARD can be cut, drilled, and sanded in the same manner and methods as most wood-based products.

​

Cutting saveBOARD does not create any toxic dust, vapors, or other potentially harmful inhalants, but we recommend you always follow Health & Safety best practices.

​​

​A Material Safety Data Sheet is available on the website.

​

Cutting & Drilling

saveBOARD Multi-Use can be cut in the same manner and methods as most wood-based products with a hand saw or power tools.

 

Cut boards upside down so skill saw leaves a clean cut on front face. We recommend using a fine tooth carbide tip saw. Sand back edge with 150grit paper.

 

T.I.P. – Allow the hole saw to cut. Do not apply excessive pressure as this may damage the back of the board upon exit.

​

Framing

All support timber framing should comply with NZS 3604 or comply with the Specific Engineering Design (S.E.D.) requirements. 90 x 45mm is the minimum timber framing size recommended for saveBOARD.

 

All steel support framing shall comply with NASH Standard Part 2:2019 Light Steel Framed Buildings or S.E.D.

 

saveBOARD Multi-Use used as an internal wall linings should be fixed at 600mm centres. We recommend a 2 4mm vertical gap between sheets to allow for thermal expansion during periods of high humidity (summer).

​

Installing on to Walls

Install the boards vertically and plumb, ensuring that the sheet edges have a minimum of 18 mm edge cover over the framing. Install with a 6 mm–10 mm clearance above the finished floor level when skirting boards are to be used. Ensure all wall insulation is installed back or flush from the framing face to be lined.

 

On a timber frame use 40 mm panel pins or 6 g screws at 150 mm centres around the sheet perimeter and 300 mm centres through the body of the sheet for non-structural applications.

 

For lightweight steel frame use self-drilling 8–10 g countersunk screws at 150 mm centres around the sheet perimeter and 300 mm centres through the body of the sheet for lightweight steel framing.

​

Installing as a Bracing Wall

Fixings On a timber frame use 6 g screws as per GIB® GS1-N fastening pattern 50, 50, 50, 75, 75,150 mm from each corner.

 

On a steel frame refer to Specific Engineered Design (S.E.D) for fixing instructions.

 

Bracing Wall Openings Small openings (i.e. 90x90mm or less). Do not make an opening within 90 mm of the sheet edge.

 

Large openings, over 90x90mm, should be placed outside of the bracing element

​

General

Heat Do not install the boards adjacent to, or behind a heat source.

​

Adhesives Common structural adhesives can be used in small daubs at 300 mm centres on the central studs for structural and non-structural board installations. An aluminum or plastic jointer may be used for aesthetic purposes. Check compatibility.

​

Jointing

Refer to our Jointing Guide that can be found on Technical Literature.

Jointing type table

For more information, refer to our website.